Can Product Backlog items in the Sprint Backlog be changed during the Sprint?

Prepare thoroughly with the Professional Scrum Master (PSM) II Test. Utilize our detailed questions and explanations to ensure exam success. Equip yourself with the skills and insights needed to excel as a Scrum Master.

The assertion that Product Backlog items in the Sprint Backlog can be changed during the Sprint, particularly when it does not affect the Sprint Goal, is grounded in Scrum's inherent flexibility and iterative nature. In Scrum, the Sprint is a time-boxed period where a team works toward delivering a potentially releasable Increment of the product.

Modifications to the Sprint Backlog are permissible, as long as they do not compromise the Sprint Goal established at the beginning of the Sprint. This means that if a change enhances the team's ability to achieve the Sprint Goal or addresses an emerging understanding of the work required, it can be executed. For example, if new insights about a feature's implementation arise or if the team identifies a more effective approach to achieving the Sprint Goal, making adjustments would not only be acceptable but encouraged.

This approach fosters an environment where teams can adapt to new information and dynamics, ultimately leading to more successful outcomes. Consequently, while changes can occur, it is essential to assess their implications on the overall objective of the Sprint, which is encapsulated in the Sprint Goal.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy