What is a key consideration for the Development Team concerning dependencies when multiple teams work from a single Product Backlog?

Prepare thoroughly with the Professional Scrum Master (PSM) II Test. Utilize our detailed questions and explanations to ensure exam success. Equip yourself with the skills and insights needed to excel as a Scrum Master.

When multiple teams are working from a single Product Backlog, a key consideration for the Development Team is the necessity to understand and minimize inter-team dependencies. This is critical because dependencies can significantly affect the ability of teams to deliver value quickly and efficiently. When teams are dependent on each other, delays or issues in one team can cascade and impact others, potentially slowing down the overall progress of the project.

By minimizing inter-team dependencies, teams can work more autonomously, enabling them to deliver increments of the product more rapidly and with less risk of being held up by the work of other teams. This concept is fundamental in agile practices, which emphasize collaboration, iterative delivery, and the ability to respond to changes quickly. Addressing dependencies proactively can lead to improved coordination among teams and a smoother workflow, essential for maintaining a healthy product delivery cadence.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy