What is expected during a Sprint Review when multiple Scrum Teams are involved?

Prepare thoroughly with the Professional Scrum Master (PSM) II Test. Utilize our detailed questions and explanations to ensure exam success. Equip yourself with the skills and insights needed to excel as a Scrum Master.

In a Sprint Review involving multiple Scrum Teams, the optimal expectation is that all teams collaborate to present an integrated increment. This approach emphasizes the collective effort and outcomes of all teams working towards a common goal, which enhances transparency and allows stakeholders to see the cumulative progress in a cohesive manner.

Presenting an integrated increment supports the Scrum values of collaboration and teamwork. It reflects the reality of how multiple teams often contribute to a shared product and provides a comprehensive overview of what has been accomplished during the Sprint. Stakeholders benefit from this integrated presentation as it allows them to gauge the overall progress and assess the interdependencies between different parts of the product, fostering a collective understanding of the work completed and the future direction.

By focusing on the integrated increment, the teams can also engage in meaningful discussions about potential difficulties, opportunities for improvement, and feedback on the features delivered, ultimately driving alignment and enhancing the product's development process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy