What is one way to ensure that a Scrum Team's Definition of Done remains relevant?

Prepare thoroughly with the Professional Scrum Master (PSM) II Test. Utilize our detailed questions and explanations to ensure exam success. Equip yourself with the skills and insights needed to excel as a Scrum Master.

One way to ensure that a Scrum Team's Definition of Done remains relevant is to review and update it at the end of each Sprint. This practice is aligned with the principles of Agile and Scrum, which emphasize regular inspection and adaptation. At the end of each Sprint, the Scrum Team reflects on their processes and outcomes during the Sprint Review and Sprint Retrospective. This is an ideal time to assess whether the existing Definition of Done adequately meets the current context and needs of the team, considering any lessons learned or changes in requirements.

By routinely reviewing the Definition of Done, the team can incorporate feedback, adapt to any changes in technology or best practices, and ensure that their standards for “done” reflect the reality of their work environment. This continuous improvement cycle reinforces the team's commitment to delivering high-quality work and maintains the relevance of their Definition of Done throughout their projects.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy