What should occur if the process deviations are detected during a Sprint?

Prepare thoroughly with the Professional Scrum Master (PSM) II Test. Utilize our detailed questions and explanations to ensure exam success. Equip yourself with the skills and insights needed to excel as a Scrum Master.

When process deviations are detected during a Sprint, adjusting the process or the material being produced is the appropriate response. This adjustment aligns with the Agile principle of continuous improvement and is fundamental to Scrum as a framework.

During a Sprint, the Scrum Team is encouraged to reflect on their work and the methods they are using to optimize efficiency and effectiveness. If issues arise, the team should analyze the situation and make necessary adjustments to their practices or the deliverables. This proactive approach helps ensure that the team can still meet the Sprint Goal and deliver value by adapting to new insights or challenges faced during the Sprint.

This response captures the essence of the Inspect and Adapt cycle intrinsic to Scrum, which emphasizes using real-time feedback to improve performance and outcomes rather than waiting for the end of the Sprint to address concerns.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy