When is the best time to review the Definition of Done if Developers believe it needs updating?

Prepare thoroughly with the Professional Scrum Master (PSM) II Test. Utilize our detailed questions and explanations to ensure exam success. Equip yourself with the skills and insights needed to excel as a Scrum Master.

The Definition of Done is a critical aspect of Scrum, as it delineates the criteria that a product increment must meet to be considered complete. When Developers think an update to the Definition of Done is needed, the best time to discuss it is during the Sprint Retrospective.

The Sprint Retrospective is specifically designed to reflect on the past Sprint and identify areas for improvement, including any adjustments to processes, tools, and the Definition of Done itself. This meeting provides an opportunity for the Development Team to collaboratively explore changes that could enhance their work and ensure that the increments produced meet quality standards.

Addressing the Definition of Done during the Sprint Retrospective allows for thoughtful discussion and consensus among the team members on what modifications are necessary, ensuring that everyone is aligned moving forward. By doing it in this context, the team can reflect on their current practices, experiments, and outcomes from the previous Sprint, leading to more informed decisions about how they define what "done" means.

Other options, while they may seem relevant, do not suit this context as well. For example, Sprint Planning is focused on setting the goals and tasks for the upcoming Sprint, while the Sprint Review aims to gather feedback on the increment produced—not necessarily reevaluating the Definition of