Which Scrum event helps the team to inspect and adapt their processes?

Prepare thoroughly with the Professional Scrum Master (PSM) II Test. Utilize our detailed questions and explanations to ensure exam success. Equip yourself with the skills and insights needed to excel as a Scrum Master.

The Sprint Retrospective is focused specifically on enabling the Scrum team to reflect on their own processes, interactions, and practices. During this event, the team examines what went well, what didn’t, and identifies opportunities for improvement. This fosters a culture of continuous improvement, allowing the team to adapt their working methods based on the insights gained from their experiences in the previous Sprint.

The purpose of the Sprint Retrospective is to inspect how the last Sprint went regarding people, relationships, processes, and tools, and then adapt accordingly for the next Sprint. This is a crucial component of the Scrum framework, as it helps ensure that teams are always evolving and striving to optimize their performance.

In contrast, while Sprint Planning is primarily about defining and organizing the work that will be done in the next Sprint, and the Sprint Review focuses on evaluating the increments of work completed with stakeholders, neither of these events is centered on the team’s internal processes. The Daily Scrum is designed for team members to synchronize their activities and plan for the day, rather than for in-depth reflection and adaptation of processes.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy